Trying to run an analysis like 6-6-16 blend and getting message that the P requirement (or some other requested nutrient) could not be met

Trying to run an analysis like 6-6-16 blend and getting message that the P requirement (or some other requested nutrient) could not be met. An example of the message is below.

  • Edit the Product Set at Blending / Setup / Product Sets. Make sure you have a product in the Product Set from which the program can pull P. If such a product does not exist in the Product Set, add one here. If you do have a product in the Product Set for P, make sure it is checked as Active. Another possibility to try would be to check the box to allow P to run over. Add the Blend Ticket again.